India Construction Cost Estimator
Estimate the construction cost for a residential project in a major Indian city. Pick a city to load indicative starting rates, replace them with your local rates, enter your floor and wall areas, and get a Bill of Quantities (BOQ) with materials, labour, wastage and GST that you can download as CSV or PDF.
India construction cost estimator
Planning aid, not a building-cost guarantee. Every bundled rate is an indicative starting value with its date; most have no published source. Enter your local rates under "Your rates" (kept in this browser) and verify all figures with local suppliers before budgeting.
Leave blank to skip.
Indicative starting rates. Enter your local rates under "Your rates".
Measured inside the walls. Use the Floor Area calculator.
Perimeter × wall height, before openings. The Net Wall Area calculator shows it as gross wall area.
Scales the bundled finishing rates (0.7, 1.0, 1.4). Your own rates are used as typed.
Typical 5 %. Complex designs may need more.
Applied to the total. Use your actual rate.
CPWD Plinth Area Rates (2012), item 3.1: 12 % of building cost for houses and flats. Replaces the plumber days line. Enter 0 or leave blank to leave plumbing out.
Assumptions
Change any value to match your product or local rules.
Basis: Typical brick wall: 230 mm. Change for block or framed construction.
Basis: Starting value from the RCC rate-analysis workbook (sheet 3). Set 0 if it is already in your rates.
Basis: Starting value from the RCC rate-analysis workbook (sheet 3), struck after the equipment charge. Set 0 if you buy materials and hire labour yourself.
- Material cost
- 335,778.00 ₹
- Labour cost
- 200,876.00 ₹
- Estimated total
- 816,642.00 ₹
- Cost per sq ft
- 1,012.00 ₹/sq ft
Estimated ₹8,16,642 at indicative Hyderabad rates (set 2026-09), standard standard, 1 floor(s).
Cost breakdown
- Materials: ₹3,35,778
- Labour: ₹2,00,876
- Wastage (5% on materials): ₹16,789
- Plumbing, water supply and sanitary (12%): ₹66,413
- Equipment (1.5%): ₹9,298
- Contractor profit and overheads (10%): ₹62,915
- GST / tax (18%): ₹1,24,572
- Total: ₹8,16,642
- Per sq ft: ₹1,012
Bill of Quantities
Rates: Hyderabad, Telangana. Bundled rates set 2026-09, indicative: enter your local rates under "Your rates".
| Item | Qty | Unit | Rate (₹) | Rate basis | Amount (₹) | Wastage (₹) | Total (₹) |
|---|---|---|---|---|---|---|---|
| Masonry | |||||||
| Bricks | 17.25 | 1000 nos | 7,000 | Indicative: enter your local rate | 1,20,750 | 6,038 | 1,26,788 |
| Cement for masonry (1:6) | 44 | bag | 480 | Indicative: enter your local rate | 21,120 | 1,056 | 22,176 |
| Coarse sand | 321 | cft | 55 | Indicative: enter your local rate | 17,655 | 883 | 18,538 |
| Reinforcement steel | 104 | kg | 72 | Indicative: enter your local rate | 7,488 | 374 | 7,862 |
| Plaster | |||||||
| Cement for plaster (12 mm, 1:6) | 20 | bag | 480 | Indicative: enter your local rate | 9,600 | 480 | 10,080 |
| Plastering labour | 3,229 | sq ft | 18 | Indicative: enter your local rate | 58,122 | 58,122 | |
| Painting | |||||||
| Primer | 41 | litre | 180 | Indicative: enter your local rate | 7,380 | 369 | 7,749 |
| Interior emulsion paint | 50 | litre | 280 | Indicative: enter your local rate | 14,000 | 700 | 14,700 |
| Painting labour | 6,458 | sq ft | 8 | Indicative: enter your local rate | 51,664 | 51,664 | |
| Flooring | |||||||
| Vitrified tile | 807 | sq ft | 95 | Indicative: enter your local rate | 76,665 | 3,833 | 80,498 |
| Flooring labour | 807 | sq ft | 20 | Indicative: enter your local rate | 16,140 | 16,140 | |
| Doors and windows | |||||||
| Door frames | 68 | rft | 320 | Indicative: enter your local rate | 21,760 | 1,088 | 22,848 |
| Door shutters | 80 | sq ft | 240 | Indicative: enter your local rate | 19,200 | 960 | 20,160 |
| Door fitting | 4 | door | 2,500 | Indicative: enter your local rate | 10,000 | 10,000 | |
| UPVC windows | 72 | sq ft | 280 | Indicative: enter your local rate | 20,160 | 1,008 | 21,168 |
| Trades | |||||||
| Mason | 81 | day | 750 | Indicative: enter your local rate | 60,750 | 60,750 | |
| Carpenter | 5 | day | 700 | Indicative: enter your local rate | 3,500 | 3,500 | |
| Electrician | 1 | day | 700 | Indicative: enter your local rate | 700 | 700 | |
| Plumbing | |||||||
| Internal water supply, drainage and sanitary installations | 12 | % of building work | 5,534.43 | Indicative: CPWD Plinth Area Rates 2012, item 3.1: 12% of building cost (residential) | 66,413 | 66,413 | |
| Subtotal (with wastage) | 6,19,856 | ||||||
| Equipment (1.5%) | 9,298 | ||||||
| Contractor profit and overheads (10%) | 62,915 | ||||||
| GST / tax (18%) | 1,24,572 | ||||||
| Total | ₹8,16,642 | ||||||
How this was calculated
- Wall volume = wall area × floors × wall thickness
- Bricks = wall volume ÷ (0.2 × 0.1 × 0.1 m) = 500 per m³ (modular 190 × 90 × 90 mm brick, 10 mm joints)
- Dry mortar = (wall volume − bricks × brick volume) × 1.33; cement = dry mortar ÷ 7 × 1440/50 ≈ 1.26 bags/m³ (1:6)
- Sand = dry mortar × 6/7, in cft
- Plaster area = wall area × 2 faces; plaster cement = area × 0.012 m × 1.33 ÷ 7 × 1440/50 ≈ 0.066 bags/m² (12 mm, 1:6)
- Door frame = doors × (2 × 7 ft + 20 sq ft ÷ 7 ft) ≈ 16.9 rft each
- Paint area = wall area × 2 faces × 2 coats
- RCC (optional): concrete, steel, formwork and labour from the RCC schedule
- Amount = quantity × rate (your rate, else the city rate)
- Wastage = material amounts × wastage %
- Plumbing (internal water supply, drainage and sanitary) = (amounts + wastage) × plumbing %; when it is on, the plumber days line is left out
- Subtotal = amounts + wastage + plumbing
- Equipment = subtotal × equipment %; profit = (subtotal + equipment) × profit %
- Tax = (subtotal + equipment + profit) × tax %
- Total = subtotal + equipment + profit + tax
- Masonry: Bricks = 17.25 1000 nos × ₹7000 = ₹1,20,750
- Masonry: Cement for masonry (1:6) = 44 bag × ₹480 = ₹21,120
- Masonry: Coarse sand = 321 cft × ₹55 = ₹17,655
- Masonry: Reinforcement steel = 104 kg × ₹72 = ₹7,488
- Plaster: Cement for plaster (12 mm, 1:6) = 20 bag × ₹480 = ₹9,600
- Plaster: Plastering labour = 3229 sq ft × ₹18 = ₹58,122
- Painting: Primer = 41 litre × ₹180 = ₹7,380
- Painting: Interior emulsion paint = 50 litre × ₹280 = ₹14,000
- Painting: Painting labour = 6458 sq ft × ₹8 = ₹51,664
- Flooring: Vitrified tile = 807 sq ft × ₹95 = ₹76,665
- Flooring: Flooring labour = 807 sq ft × ₹20 = ₹16,140
- Doors and windows: Door frames = 68 rft × ₹320 = ₹21,760
- Doors and windows: Door shutters = 80 sq ft × ₹240 = ₹19,200
- Doors and windows: Door fitting = 4 door × ₹2500 = ₹10,000
- Doors and windows: UPVC windows = 72 sq ft × ₹280 = ₹20,160
- Trades: Mason = 81 day × ₹750 = ₹60,750
- Trades: Carpenter = 5 day × ₹700 = ₹3,500
- Trades: Electrician = 1 day × ₹700 = ₹700
- Plumbing: Internal water supply, drainage and sanitary installations = 12% × ₹5,53,443 of building work above = ₹66,413
How to use this estimator
Start by selecting your city: the calculator loads indicative starting rates, each shown with the month it was set. Enter your carpet floor area and gross wall area per floor (you can measure these from the Floor Planner), then the number of doors, windows and floors. Choose a construction standard: basic, standard or good, which scales the bundled finishing rates.
The calculator builds a Bill of Quantities from your inputs: bricks, cement, sand and steel for the masonry; plaster, primer, paint and tiles for the finish; plus labour for masonry, carpentry and electrical work, and a plumbing line for water supply, drainage and sanitary work. You can add RCC columns, PCC and earthwork. Under "Your rates", replace any bundled rate with a quote you have; your inputs are kept in this browser. Wastage is added on materials, then the equipment charge and contractor profit, then GST. Download the BOQ as CSV or PDF.
What the estimate covers
The estimate covers the main construction activities for a typical load-bearing brick masonry house: masonry (bricks, cement, sand, steel), plastering, internal painting, vitrified tile flooring, doors, UPVC windows, trade labour (mason, carpenter, electrician) and a plumbing line for internal water supply, drainage and sanitary installations. Optionally it adds RCC columns (concrete materials, reinforcement, formwork and labour), PCC, excavation and backfilling.
It does not cover footings, beams, slabs, structural design, outside water and sewer connections, electrical wiring and fixtures, carpentry beyond doors, or architectural and engineering fees.
Understanding the rate tables
Every bundled rate is an indicative starting value, not a quotation, and the table shows the month it was set. The RCC rates for Hyderabad come from the InsightHub Construction Estimation Master Toolkit. The other rates, and the city index that scales Hyderabad figures to the other cities, have no published source, and the table labels them "enter your local rate". Excavation and backfilling ship at zero: enter your rate per cubic metre.
Prices differ by brand, quality, quantity, season and bargaining power, so replace the bundled figures with your own quotes. The standard selector multiplies the bundled finishing rates by 0.7 (basic), 1.0 (standard) or 1.4 (good); rates you enter are used as typed.
Plumbing: water supply, drainage and sanitary
The plumbing line covers the pipes, fittings and labour for water supply, drainage and sanitary fittings inside the house. It is priced as a percentage of the building work the estimate has already priced (masonry, plaster, paint, flooring, doors, windows, trade labour and any RCC), because that is how the Central Public Works Department prices it. CPWD Plinth Area Rates 2012, item 3.1 "Internal water supply & sanitary installations", sets 12 % of the cost of the normal building for every type of residential quarter (4 % for offices and hospitals, 10 % for schools, 5 % for hostels). It is the latest Plinth Area Rates edition on the publications page of cpwd.gov.in.
The estimator starts at 12 %. If the other lines come to ₹10,00,000, plumbing adds ₹1,20,000, and the equipment charge, profit and GST then apply to it as to every other line. With the plumbing line on, the separate plumber days line is left out so the plumber is not counted twice. The estimate leaves out footings, slabs and the roof, so 12 % of a smaller base gives a lower plumbing figure than a full-house quote: if your plumber quotes per point or per bathroom, work out the percentage from the quote and enter it, or enter 0 to leave plumbing out.
Next steps
Treat the estimate as a starting point for talking to contractors, not as a final number. For a closer BOQ, draw your floor plan in the Floor Planner, measure the floor and wall areas there and enter them here. Then get a detailed quote for each line item and add a contingency (typically 5-10% of the total) for unforeseen costs.
Frequently asked questions
How accurate is this construction cost estimator?
It is a planning aid, not a quote. The result is based on indicative rate tables for your chosen city and simplified quantity assumptions. Actual costs depend on design complexity, material quality, contractor, location within the city, and market conditions. Always verify with local suppliers and contractors before budgeting.
Which cities are covered?
Hyderabad, Bangalore, Delhi, Mumbai, Chennai, Kolkata, Pune and Ahmedabad. Every table is indicative: the other cities are Hyderabad figures scaled by a city index that has no published source. Enter your own rates for the city you are building in.
What does cost per sq ft include?
The cost per sq ft shown includes materials, labour, the wastage allowance, the equipment charge (1.5 % by default), contractor profit and overheads (10 % by default, on the subtotal plus equipment) and GST, based on the quantities the calculator derives from your inputs. It covers superstructure and finishes for a typical residential build. It includes the plumbing line (12 % of the building work by default) but not land cost, foundation, electrical wiring or professional fees unless you add those separately.
Does this include plumbing?
Yes. A plumbing line for internal water supply, drainage and sanitary installations is added at 12 % of the building work the estimate prices, the figure CPWD Plinth Area Rates 2012 (item 3.1) give for residential buildings. Change the percentage to match your plumber's quote, or enter 0 to leave it out. Outside water and sewer connections are not included.
How do I measure my wall area accurately?
Use the Net Wall Area Calculator. Measure each wall's length and height and enter them; its gross wall area (before doors and windows) is the figure this estimator asks for. Enter one floor's wall area here: the estimator multiplies it by the number of floors. If your floors differ, enter their average.